Quarterly Activities/Appendix 5B Cash Flow Report
Released
Released
Announcement PDF
ACN: 124 279 750 E: info@victorymetalsaustralia.com D: +61 (08) 6555 2950 A: Suite 1, 295 Rokeby Road, Subiaco, WA, 6008
— T H E F U T U R E O F A U S T R A L I A N R A R E E A R T H S —
ASX RELEASE
1 5 J a n u a r y 2 0 2 6
Quarterly Activities Report – 31 December 2025
Victory Metals (ASX:VTM) (Victory or the Company) is pleased to report on its activities and the
Appendix 5B for the quarter ending 31 December 2025 (Quarter, Reporting Period).
Highlights
▪ Breakthrough metallurgical results from the North Stanmore Project, with ~80% of rare earths
leached within 30 minutes compared to the previous four-hour assumption
▪ The up to eight times shorter leach time is expected to reduce North Stanmore’s CAPEX and
OPEX through a smaller leach circuit, with further testing at a 15-minute interval underway
▪ Significant grade increases delivered in Terbium (Tb), Dysprosium (Dy) and Scandium (Sc)
through a simple beneficiation and straightforward -10.8 μm cyclosizing (no complex reagents
or expensive circuits), materially enriching these key critical minerals
▪ North Stanmore clears environmental milestone, with comprehensive baseline studies
completed across flora, fauna, surface water, groundwater, soils and waste characterisation
▪ Letter of Intent (LOI) signed with Sumitomo Corporation to advance offtake and strategic
cooperation for the North Stanmore Project
▪ United States President Donald Trump’s former Deputy Chief of Staff, Emma Doyle, appointed
as Victory’s Senior Advisor for U.S. Strategic Engagement
NORTH STANMORE HEAVY RARE EARTH ELEMENTS PROJECT
As one of the largest heavy rare earth clay projects globally, the North Stanmore Project (North
Stanmore or the Project) presents a unique opportunity to establish a long-term, low-cost supply of
critical minerals essential for high-growth industries including renewable energy, electric vehicles
and defence.
North Stanmore is located in the Tier-1 mining jurisdiction of Western Australia, where both Federal
and State Governments have committed billions of dollars of support for rare earth projects1. The
Project is strategically positioned to become a potential producer of heavy rare earth elements and
critical minerals which are subject to export restrictions from China, including dysprosium, terbium
and yttrium.
1 https://www.exportfinance.gov.au/newsroom/transforming-australia-s-critical-minerals-sector/
ACN: 124 279 750 E: info@victorymetalsaustralia.com D: +61 (08) 6555 2950 A: Suite 1, 295 Rokeby Road, Subiaco, WA, 6008
— T H E F U T U R E O F A U S T R A L I A N R A R E E A R T H S —
Figure 1. Location of Victory Metals’ North Stanmore Project
GLOBALLY OUTSTANDING LEACH RESULTS
In December, Victory announced it had received kinetic leach results showing a major reduction in
leach time for the North Stanmore Project, with ~80% of rare earths leached in 30 minutes
compared to the four-hour assumption used in the Scoping Study.
The rapid leach kinetics confirm a clear pathway to a smaller leach circuit, lower reagent
consumption and improved process efficiency.
Kinetic leach test results
The latest test results confirm that rapid leaching kinetics provide a critical window for high REE
extraction while minimising reagent consumption from dissolving gangue.
The key finding is the result of kinetic testing, with the earliest measured point at just 30 minutes.
Further testing is underway using shorter measurement times.
ACN: 124 279 750 E: info@victorymetalsaustralia.com D: +61 (08) 6555 2950 A: Suite 1, 295 Rokeby Road, Subiaco, WA, 6008
— T H E F U T U R E O F A U S T R A L I A N R A R E E A R T H S —
Figure 2: Graph showing rapid extraction rates.
Time vs. Extraction
The test results show that the minimal increase in REE recovery gained by extending the leach time
is heavily outweighed by the significantly increased dissolution of impurities.
Extraction rates (%)
HY20845
30 min
HY20845
4hr
Variance
TREY
%
78.2 81.3 3.1
Fe % 42.1 70.3 28.2
Al % 12.8 21.1 8.3
Si % 0.3 0.3 0
Ca % 73.8 77.3 3.5
Mg % 83 94.2 11.2
Na % 6.9 7.5 0.6
K % 16 26.3 10.3
Th % 42.2 39.9 -2.3
U % 65.9 72.9 7
Table 1: Summary of extraction rates
Victory can achieve ~80% of its rare earth extraction in the first 30 minutes from a composite sample
across North Stanmore. By adopting a 30-minute leach duration, Victory will avoid unnecessary
consumption of reagents, resulting in a massive operational saving. This translates directly to a
ACN: 124 279 750 E: info@victorymetalsaustralia.com D: +61 (08) 6555 2950 A: Suite 1, 295 Rokeby Road, Subiaco, WA, 6008
— T H E F U T U R E O F A U S T R A L I A N R A R E E A R T H S —
lower reagent cost and a simplified downstream purification circuit, significantly improving the
project's overall economics.
Next steps
• Completion of additional kinetic optimisation testwork.
• Engineering updates to incorporate revised leach parameters.
• Integration of new data into the Pre-Feasibility Study scheduled for release in 2026.
SIGNIFICANT NORTH STANMORE GRADE INCREASES IN TERBIUM & DYSPROSIUM
Victory reported that simple, low-cost size-by-fraction separation (-10.8 μm) on ore from the North
Stanmore Project has delivered substantial grade improvements in three critical elements directly
linked to China’s latest bans on defence and high-tech supply chains: Terbium (Tb), Dysprosium (Dy)
and Scandium (Sc).
Size by fraction beneficiation
ALS Metallurgy Perth carried out simple wet classification to isolate the -10.8 μm fraction by
cyclosizing from a bulk sample composited from the North Stanmore resource area2. Grades were
assayed on head and fraction products. No chemical upgrading or complex mineral separation was
applied.
Feed Grade
(ppm)
<10.8 µm
Fraction (ppm)
Percent
Change (%)
Tb4O7 8 13 >50.0
Dy2O3 55 73 >33.3
Sc2O3 46 92 >100.0
TREO 1484 2104 >41.8
HREO/TREO 0.43 0.41 <-3.2
HREO – Eu2O3, Gd2O3, Tb4O7, Dy2O3, Ho2O3, Er2O3, Tm2O3, Yb2O3, Lu2O3 and Y2O3
Cyclosizing the feed ore to a <10.8 μm fraction resulted in a 42% increase in grade, a 50% increase
in Tb4O7, a 33% increase in Dy2O3, and a 100% increase in Sc2O3. The HREO/TREO ratio remained
essentially constant at 41%.
Results demonstrate intrinsic deportment of key critical elements into ultrafine particles. This ~73%
decrease in mass to be processed provides a low-CAPEX, low-OPEX front-end upgrade option that
reduces throughput of less critical elements and gangue materials.
Defence uses for Terbium, Dysprosium and Scandium
Terbium (Tb)
• Essential component of high-temperature permanent magnets (NdFeB) used in hypersonic
missiles, fighter jet actuators, submarine systems, drones, radar, sonar and guidance
systems.
• Provides thermal stability and strength for weapons grade magnetics.
Dysprosium (Dy)
• Critical additive to increase coercivity and temperature in permanent magnets, enabling
them to operate under extreme heat and stress.
2 Refer to ASX announcement dated 11 August 2025 titled “UPDATED MRE IDENTIFIES HREO/TREO RATIOS UP TO 83%”
ACN: 124 279 750 E: info@victorymetalsaustralia.com D: +61 (08) 6555 2950 A: Suite 1, 295 Rokeby Road, Subiaco, WA, 6008
— T H E F U T U R E O F A U S T R A L I A N R A R E E A R T H S —
• Used in EV traction motors, defence aircraft, naval propulsion, precision guided munitions
and missile defence systems.
Scandium (Sc)
• When alloyed with aluminium, produces lightweight, high-strength Al-Sc alloys for
aerospace frames, fighter jets, naval vessels and advanced defence structures.
• Improves fuel efficiency and durability in military aircraft.
• Also used in solid oxide fuel cells relevant to military energy resilience.
NORTH STANMORE CLEARS ENVIRONMENTAL MILESTONE
Victory advised it had completed baseline environmental and biological studies at the North
Stanmore Project. The results reinforced North Stanmore’s strong development credentials and
provided a high level of confidence for stakeholders, with studies to date confirming no
environmental impediments that impact advancing the Project.
The positive findings demonstrated that North Stanmore could progress responsibly and
sustainably, strengthening Victory’s potential as a future supplier of heavy rare earths outside of
China, aligning with Western supply chain security and global demand for ethical, low-impact
resources.
Victory commissioned multiple expert consultancy firms to provide comprehensive baseline
biological (flora, fauna, subterranean) and biophysical studies (surface water, groundwater, soils,
and waste characterisation) across the North Stanmore Project area. Results were highly
encouraging with no threatened Flora or Ecological Communities recorded.
Surface water flows have also been identified as being consistent with regional norms and can be
successfully managed and groundwater studies indicate no surplus water generation, with the
project outside of the Cue township’s drinking water supply area.
ACN: 124 279 750 E: info@victorymetalsaustralia.com D: +61 (08) 6555 2950 A: Suite 1, 295 Rokeby Road, Subiaco, WA, 6008
— T H E F U T U R E O F A U S T R A L I A N R A R E E A R T H S —
CORPORATE
VICTORY & SUMITOMO ADVANCE RARE EARTH PARTNERSHIP
Victory announced it had entered into a non-binding Letter of Intent (LOI) with Sumitomo
Corporation, one of Japan’s most powerful and globally recognised trading houses, to advance
offtake and strategic cooperation for the North Stanmore Project.
This LOI marked a transformational step in Victory’s journey, building on the non-binding
Memorandum of Understanding (MOU) signed in December 20243 and taking the relationship with
Sumitomo to a more defined level. The LOI signing sets the stage for binding offtake negotiations.
The LOI outlines the offtake framework for North Stanmore’s Mixed Rare Earth Product, with Victory
to supply up to 30% of annual production, or 1,000 tonnes per year of MREC, including up to 50
tonnes DyTb product for an initial five-year term. Sales to Sumitomo from pilot plant operations are
expected to commence in 2027 ahead of commercial production.
The December 2024 MOU, which expires on 31 October 2025, represented the first stage of
engagement. Entering into an LOI is the natural and critical next step in such transactions.
Sumitomo’s decision to formalise this LOI instead demonstrates a clear vote of confidence in
Victory’s North Stanmore Project and highlights a continued interest in working towards long-term
strategic cooperation.
VICTORY ENGAGES PRESIDENT DONALD TRUMP’S FORMER DEPUTY CHIEF OF STAFF
Victory announced the appointment of Emma Doyle as Senior Advisor for U.S. Strategic
Engagement, providing the Company with direct insight into U.S. policy and government affairs at a
pivotal time for the rare earths sector.
Emma Doyle served as Principal Deputy Chief of Staff to the President of the United States where
she directed core West Wing functions and advised the President and his senior leadership team.
She also held senior roles at the White House Office of Management and Budget and in the Office
of First Lady Melania Trump.
Her engagement followed the landmark agreement between President Donald J. Trump and Prime
Minister Anthony Albanese, where the U.S. and Australia announced billions of dollars in joint
investment to build allied rare earth and critical minerals supply chains. Victory’s position as
Australia’s largest clay-hosted heavy rare earth project aligns directly with this new geopolitical
framework.
ANNUAL GENERAL MEETING
Victory announced the results of its Annual General Meeting held on 19 November 2025. All
resolutions were passed by a poll.
Details of each resolution and proxy votes are included in the VTM ASX Announcement dated 19
November 2025 in accordance with the requirements of ASX Listing Rule 3.13.2 and section 251AA
of the Corporations Act 2001.
3
Refer to ASX Announcement dated 17th December 2024 titled “Strategic Offtake MOU Signed with Fortune Global 500 Leader Sumitomo
Corporation.
ACN: 124 279 750 E: info@victorymetalsaustralia.com D: +61 (08) 6555 2950 A: Suite 1, 295 Rokeby Road, Subiaco, WA, 6008
— T H E F U T U R E O F A U S T R A L I A N R A R E E A R T H S —
CASHFLOWS FOR THE QUARTER
Attached to this report is the Appendix 5B containing the Company’s cash flow statement for the
December 2025 quarter. Exploration expenditure of $1.22M mainly related to exploration activities
undertaken at North Stanmore REE Project net of GST refunds received on current and previous
exploration expenditure. $649k expenditure net of GST refunds received on current and previous
administration expenditure and corporate costs of which $168k were payments made to related
parties. These payments relate to the remuneration agreements for Executive and Non-Executive
Directors and to SmallCap Corporate Pty Ltd (SmallCap) for providing company secretary,
accounting and office services to the Company. Non-Executive Chairman James Bahen is a
shareholder and director of SmallCap.
As at 31 December 2025, the Company had available cash of approximately $13.56M.
December 2025 Quarter – ASX Announcements
This Quarterly Activities Report contains information extracted from ASX market announcements
reported in accordance with the 2012 edition of the “Australasian Code for Reporting of Exploration
Results, Mineral Resources and Ore Reserves” (2012 JORC Code). Further details (including 2012
JORC Code reporting tables where applicable) of exploration results referred to in this Quarterly
Activities Report can be found in the following announcements lodged on the ASX:
01/12/2025 Victory Delivers Global Outstanding Leach Results
19/11/2025 Results of Annual General Meeting
28/10/2025 Victory Engages President Donald Trump’s Former Deputy Chief of Staff
21/10/2025 Significant North Stanmore Grade Increases in Heavy Rare Earths
06/10/2025 North Stanmore Clears Environmental Milestone
01/10/2025 Victory & Sumitomo Advance Rare Earth Partnership
These announcements are available for viewing on the Company’s website
www.victorymetalsaustralia.com. Victory confirms that it is not aware of any new information or
data that materially affects the information included in any original ASX announcement.
This announcement has been authorised by the Board of Victory Metals Limited.
For further information please contact:
Brendan Clark Ben Creagh
CEO and Executive Director Investor and Media Relations
info@victorymetalsaustralia.com benc@nwrcommunications.com.au
Victory Metals Limited
Victory is dedicated to the exploration and development of its flagship North Stanmore Heavy Rare
Earth Elements (HREE), Scandium, Hafnium and Gallium Project located in the Cue Region of
Western Australia. The Company is committed to advancing this world-class project to unlock its
significant potential.
ACN: 124 279 750 E: info@victorymetalsaustralia.com D: +61 (08) 6555 2950 A: Suite 1, 295 Rokeby Road, Subiaco, WA, 6008
— T H E F U T U R E O F A U S T R A L I A N R A R E E A R T H S —
In August 2025, Victory Metals announced a robust Mineral Resource Estimate (MRE) for North
Stanmore, totalling 320.6 million tonnes, with the majority of the resource, classified in the indicated
category. This positions the North Stanmore Project as Australia's largest indicated clay heavy rare
earth resource, underscoring its pivotal role as a future supplier of critical materials for the future.
North Stanmore Mineral Resource Estimate
Table 1: North Stanmore August 2025 MRE (≥330ppm TREO + Sc2O3 cut-off grade)
CLASSIFICATION
MRE TONNES
(t)
TREOSc
(ppm)
TREO
(ppm)
HREO
(ppm)
LREO
(ppm)
HREO/TREO
(%)
Sc2O3
(ppm)
Ga2O3
(ppm)
INDICATED 176,522,000 532 505 190 316 39 26 26
INFERRED 144,118,000 484 463 166 297 37 21 25
TOTAL 320,640,000 510 486 179 307 38 24 26
Numbers are rounded to reflect they are an estimate. Numbers may not sum due to rounding.
Competent Person Statement
Professor Ken Collerson
Statements contained in this report relating to exploration results, Mineral Resource Estimate,
scientific evaluation, and potential, are based on information compiled and evaluated by Professor
Ken Collerson. Professor Collerson (PhD) Principal of KDC Geo Consulting, and a Fellow of the
Australasian Institute of Mining and Metallurgy (AusIMM - membership number 100125), is a
geochemist/geologist with sufficient relevant experience in relation to rare earth element and critical
metal mineralisation being reported on, to qualify as a Competent Person as defined in the Australian
Code for Reporting of Identified Mineral Resources and Ore reserves (JORC Code 2012). Professor
Collerson consents to the use of this information in this report in the form and context in which it
appears.
The Company confirms that it is not aware of any new information or data that materially affects the
information included in the original market announcements in relation to the exploration results.
The Company confirms that the form and context in which the competent persons findings have not
been materially modified from the original announcement
ACN: 124 279 750 E: info@victorymetalsaustralia.com D: +61 (08) 6555 2950 A: Suite 1, 295 Rokeby Road, Subiaco, WA, 6008
— T H E F U T U R E O F A U S T R A L I A N R A R E E A R T H S —
Appendix 1 – Interest in Mining Tenements
Tenement
ID
Status Location
Interest at the beginning
of the quarter
Interest
acquired
or
disposed
Interest at the end of
the quarter
E20/1016 Live Cue 100% - 100%
E20/1053 Application Cue 100% beneficial - 100% beneficial
E20/1080 Application Cue 100% beneficial - 100% beneficial
E20/1081 Application Cue 100% beneficial - 100% beneficial
E20/871 Live Cue 100% - 100%
E20/971 Live Cue 100% - 100%
E51/1939 Live Cue 100% 100% -
E51/2102 Live Cue 100% 100% -
E51/2104 Live Cue 100% 100% -
G20/25 Live Cue 100% - 100%
L20/72 Application Cue 100% beneficial - 100% beneficial
M20/128 Live Cue 100% - 100%
M20/129 Live Cue 100% - 100%
M20/288 Live Cue 100% - 100%
M20/305 Live Cue 100% - 100%
M20/327 Live Cue 100% 100% -
M20/360 Live Cue 100% 100% -
M20/455 Live Cue 100% - 100%
M20/480 Live Cue 100% - 100%
M20/494 Live Cue 100% - 100%
M20/543 Live Cue 100% - 100%
M20/544 Live Cue 100% - 100%
M20/546
Application Cue 100%-conversion interest
(P20/2007)
-
100%
M20/550
Application Cue 100%-conversion interest-
(P20/2153)
-
100%
M20/564 Application Cue 100% beneficial - 100% beneficial
M21/125 Live Cue 100% - 100%
M21/143 Live Cue 100% - 100%
M21/158 Live Cue 100% - 100%
M21/26 Live Cue 100% - 100%
M21/86 Live Cue 100% - 100%
M21/94 Live Cue 100% - 100%
M21/95 Live Cue 100% - 100%
P20/2007 Live Cue 100% - 100%
P20/2153 Live Cue 100% - 100%
P20/2248 Live Cue 100% - 100%
P20/2249 Live Cue 100% - 100%
P20/2250 Live Cue 100% - 100%
P20/2331 Live Cue 100% - 100%
P20/2333 Live Cue 100% - 100%
P20/2334 Live Cue 100% - 100%
P20/2345 Live Cue 100% - 100%
P20/2346 Live Cue 100% - 100%
ACN: 124 279 750 E: info@victorymetalsaustralia.com D: +61 (08) 6555 2950 A: Suite 1, 295 Rokeby Road, Subiaco, WA, 6008
— T H E F U T U R E O F A U S T R A L I A N R A R E E A R T H S —
P20/2352 Live Cue 100% - 100%
P20/2353 Live Cue 100% - 100%
P20/2354 Live Cue 100% - 100%
P20/2355 Live Cue 100% - 100%
P20/2356 Live Cue 100% - 100%
P20/2357 Live Cue 100% - 100%
P20/2358 Live Cue 100% - 100%
P20/2359 Live Cue 100% - 100%
P20/2360 Live Cue 100% - 100%
P20/2383 Live Cue 100% - 100%
P20/2397 Live Cue 100% - 100%
P20/2398 Live Cue 100% - 100%
P20/2402 Live Cue 100% - 100%
P20/2403 Live Cue 100% - 100%
P20/2409 Live Cue 100% - 100%
P20/2410 Live Cue 100% - 100%
P20/2468 Live Cue 100% - 100%
P20/2469 Live Cue 100% - 100%
P20/2486 Live Cue 100% - 100%
P21/772 Live Cue 100% - 100%
P21/773 Live Cue 100% - 100%
P21/774 Live Cue 100% - 100%
P21/775 Live Cue 100% - 100%
P21/776 Live Cue 100% - 100%
P21/793 Live Cue 100% - 100%
P20/2534 Application Cue 100% beneficial - 100% beneficial
P46/1975 Live Nullagine 100% - 100%
P46/1976 Live Nullagine 100% - 100%
Rule 5.5
ASX Listing Rules Appendix 5B (17/07/20) Page 1
+ See chapter 19 of the ASX Listing Rules for defined terms.
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
Victory Metals Limited
ACN Quarter ended (“current quarter”)
124 279 750 31 December 2025
Consolidated statement of cash flows Current quarter
$A’000
Year to date
(6 months)
$A’000
1. Cash flows from operating activities
- -
1.1 Receipts from customers
1.2 Payments for
- -
(a) exploration & evaluation
(b) development - -
(c) production - -
(d) staff costs (31) (49)
(e) administration and corporate costs (618) (1,240)
1.3 Dividends received (see note 3) - -
1.4 Interest received 124 162
1.5 Interest and other costs of finance paid - -
1.6 Income taxes paid - -
1.7 Government grants and tax incentives - -
1.8 Other (provide other details) – R&D Receipt - -
1.9 Net cash from / (used in) operating
activities
(525) (1,127)
2. Cash flows from investing activities
- -
2.1 Payments to acquire or for:
(a) entities
(b) tenements - -
(c) property, plant and equipment - -
(d) exploration & evaluation (1,220) (2,918)
(e) investments - -
(f) other non-current assets - -
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 2
+ See chapter 19 of the ASX Listing Rules for defined terms.
Consolidated statement of cash flows Current quarter
$A’000
Year to date
(6 months)
$A’000
2.2 Proceeds from the disposal of:
- -
(a) entities
(b) tenements - -
(c) property, plant and equipment - -
(d) investments - -
(e) other non-current assets - -
2.3 Cash flows from loans to other entities - -
2.4 Dividends received (see note 3) - -
2.5 Other (provide other details) – Lease
Deposit
- -
2.6 Net cash from / (used in) investing
activities
(1,220) (2,918)
3. Cash flows from financing activities
250 11,750
3.1 Proceeds from issues of equity securities
(excluding convertible debt securities)
3.2 Proceeds from issue of convertible debt
securities
- -
3.3 Proceeds from exercise of options - -
3.4 Transaction costs related to issues of equity
securities or convertible debt securities
(38) (604)
3.5 Proceeds from borrowings - -
3.6 Repayment of borrowings - -
3.7 Transaction costs related to loans and
borrowings
- -
3.8 Dividends paid - -
3.9a Proceeds from issues of equity securities to
be allotted
- -
3.9b Repayment of lease liabilities - -
3.10 Net cash from / (used in) financing
activities
212 11,146
4. Net increase / (decrease) in cash and
cash equivalents for the period
4.1 Cash and cash equivalents at beginning of
period
15,096 6,462
4.2 Net cash from / (used in) operating
activities (item 1.9 above)
(525) (1,127)
4.3 Net cash from / (used in) investing activities
(item 2.6 above)
(1,220) (2,918)
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 3
+ See chapter 19 of the ASX Listing Rules for defined terms.
Consolidated statement of cash flows Current quarter
$A’000
Year to date
(6 months)
$A’000
4.4 Net cash from / (used in) financing activities
(item 3.10 above)
212 11,146
4.5 Effect of movement in exchange rates on
cash held
- -
4.6 Cash and cash equivalents at end of
period
13,563 13,563
5. Reconciliation of cash and cash
equivalents
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
Current quarter
$A’000
Previous quarter
$A’000
5.1 Bank balances 6,613 2,596
5.2 Call deposits 6,950 12,500
5.3 Bank overdrafts
5.4 Other (provide details)
5.5 Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
13,563 15,096
6. Payments to related parties of the entity and their
associates
Current quarter
$A'000
6.1 Aggregate amount of payments to related parties and their
associates included in item 1*
168
6.2 Aggregate amount of payments to related parties and their
associates included in item 2
-
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an
explanation for, such payments.
* Payments in relation to Director’s fees for the period.
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 4
+ See chapter 19 of the ASX Listing Rules for defined terms.
7. Financing facilities
Note: the term “facility’ includes all forms of financing
arrangements available to the entity.
Add notes as necessary for an understanding of the
sources of finance available to the entity.
Total facility
amount at quarter
end
$A’000
Amount drawn at
quarter end
$A’000
7.1 Loan facilities - -
7.2 Credit standby arrangements - -
7.3 Other (please specify) - -
7.4 Total financing facilities - -
7.5 Unused financing facilities available at quarter end
7.6 Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing
facilities have been entered into or are proposed to be entered into after quarter end,
include a note providing details of those facilities as well.
8. Estimated cash available for future operating activities $A’000
8.1 Net cash from / (used in) operating activities (item 1.9) (525)
8.2 (Payments for exploration & evaluation classified as investing
activities) (item 2.1(d))
(1,220)
8.3 Total relevant outgoings (item 8.1 + item 8.2) (1,745)
8.4 Cash and cash equivalents at quarter end (item 4.6) 13,563
8.5 Unused finance facilities available at quarter end (item 7.5) -
8.6 Total available funding (item 8.4 + item 8.5) 13,563
8.7 Estimated quarters of funding available (item 8.6 divided by
item 8.3)
7.77
Note: if the entity has reported positive relevant outgoings (ie a net cash inflow) in item 8.3, answer item 8.7 as “N/A”.
Otherwise, a figure for the estimated quarters of funding available must be included in item 8.7.
8.8 If item 8.7 is less than 2 quarters, please provide answers to the following questions:
8.8.1 Does the entity expect that it will continue to have the current level of net operating
cash flows for the time being and, if not, why not?
Answer: N/A
8.8.2 Has the entity taken any steps, or does it propose to take any steps, to raise further
cash to fund its operations and, if so, what are those steps and how likely does it
believe that they will be successful?
Answer: N/A
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 5
+ See chapter 19 of the ASX Listing Rules for defined terms.
8.8.3 Does the entity expect to be able to continue its operations and to meet its business
objectives and, if so, on what basis?
Answer: N/A
Note: where item 8.7 is less than 2 quarters, all of questions 8.8.1, 8.8.2 and 8.8.3 above must be answered.
Compliance statement
1 This statement has been prepared in accordance with accounting standards and policies which
comply with Listing Rule 19.11A.
2 This statement gives a true and fair view of the matters disclosed.
Date: .........15 January 2026.........
Authorised by: ..........The Board of Directors of the Company.................................
(Name of body or officer authorising release – see note 4)
Notes
1. This quarterly cash flow report and the accompanying activity report provide a basis for informing the market about the
entity’s activities for the past quarter, how they have been financed and the effect this has had on its cash position. An
entity that wishes to disclose additional information over and above the minimum required under the Listing Rules is
encouraged to do so.
2. If this quarterly cash flow report has been prepared in accordance with Australian Accounting Standards, the definitions
in, and provisions of, AASB 6: Exploration for and Evaluation of Mineral Resources and AASB 107: Statement of Cash
Flows apply to this report. If this quarterly cash flow report has been prepared in accordance with other accounting
standards agreed by ASX pursuant to Listing Rule 19.11A, the corresponding equivalent standards apply to this report.
3. Dividends received may be classified either as cash flows from operating activities or cash flows from investing activities,
depending on the accounting policy of the entity.
4. If this report has been authorised for release to the market by your board of directors, you can insert here: “By the board”.
If it has been authorised for release to the market by a committee of your board of directors, you can insert here: “By the
[name of board committee – eg Audit and Risk Committee]”. If it has been authorised for release to the market by a
disclosure committee, you can insert here: “By the Disclosure Committee”.
5. If this report has been authorised for release to the market by your board of directors and you wish to hold yourself out as
complying with recommendation 4.2 of the ASX Corporate Governance Council’s Corporate Governance Principles and
Recommendations, the board should have received a declaration from its CEO and CFO that, in their opinion, the financial
records of the entity have been properly maintained, that this report complies with the appropriate accounting standards
and gives a true and fair view of the cash flows of the entity, and that their opinion has been formed on the basis of a
sound system of risk management and internal control which is operating effectively.
Share your feedback